CASE STUDIES

Major Dewatering Infrastructure

ABOUT THE PROJECT

Silverstone were engaged to Design, Supply, Install and Commission Major Dewatering Infrastructure project for a well-known mining company in the Pilbara Region. Our Scope included the Design, Mechanical, Electrical, Civil and Commissioning of the large water project. Silverstone exceeded our client’s expectations by completing the project safely, on time and within agreed budgets. The project was delivered months in advance of the clients expectations unlocking huge Iron Ore value.

TYPE

Mechanical, Electrical, Civil

LOCATION

Pilbara, WA

PERSONNEL

20

SCOPE

  • 15Km of Supply and Installation of HDPE (DN710, DN315)
  • Various Steel Manifolds, Reducers, Air Valves
  • 1 x Supply and Installation of 420kl tank
  • 11 x Installation of Dewatering packages
  • 8 x Road crossings HV/LV
  • 1 x Electrical control systems
  • Testing and commissioning

Outcome

Compliance

Compliance with all Health, Safety, Environment and Community requirements.